By Stephen Candia –Arua
Reconstruction of the power dam at Nyagak in the newly created Zombo district has resumed amid protest by some locals over compensation for their land.
During a visit by officials from Arua district local government, Arua Municipal council, NRM office Arua, West Nile Rural electrification company ltd, 409 brigade commander and team, the Diso Arua, Wenreco, Zombo district to the site yesterday (Monday 18th April), it was found out at least 20 households are still demanding for compensation totaling to Fourty five million Uganda shillings.
The impromptu visit, which coincided with the monthly site meeting of Nyagak power project later generated a heated debate at Sky-Lux hotel in Paidha town between the West Nile leaders and officials from Electricity regulatory authority-ERA, Spencon Constructors, and Wenreco officials,